FORCRETE Panel Patch 20kg
Structural repair mortar that goes on 3 to 100 mm in one pass, overhead included. 70 MPa at 28 days.
FORCRETE 100 is a single-component, polymer-modified, fibre-reinforced repair mortar for putting concrete back on columns, beams, walls and soffits. It holds 3 to 100 mm in a single pass, vertical, overhead or horizontal, without formwork, and meets the EN 1504-3 Class R4 thresholds on Forspec R&D data. 20 kg bag.
Where to use it
- Spalled or damaged concrete on columns, beams, walls and soffits
- Patching around corroded reinforcement
- Bridge decks, tunnels, marine and water-exposed structures
- Prime with ACTFLEX 300, or ACTFLEX EP250 where the repair will be damp or immersed
Why waterproofers buy it
- About 25 MPa at 1 day, 51 MPa at 7 days, 70 MPa at 28 days
- Shrinkage-compensated. Bond to concrete above 2.0 MPa
- Resists carbonation, chloride ingress, abrasion and freeze-thaw (300 cycles, ASTM C666)
- Hand, trowel or wet-spray. Pot life 30 to 40 minutes, foot traffic at 24 hours
- 10 year Forspec product warranty
Coverage
About 1.8 kg of powder per m² per mm. A 20 kg bag with 3.6 L of water gives about 11.2 L of mortar: roughly 1.1 m² at 10 mm or 0.45 m² at 25 mm.
Not for
Unstable or moving substrates, concrete under 28 days old, below 5°C or above 35°C, more than 3.6 L of water per bag, re-tempering stiffened mortar, or skipping the 72 hour cure under ACTFLEX CURESEAL or damp hessian and plastic.
All times at 25°C and 50% RH.
Technical overview
- FORCRETE 100 is a single-component, polymer-modified, fibre-reinforced structural repair mortar for reinstating concrete on columns, beams, walls and soffits.
- Its thixotropic body places from 3 mm up to 100 mm in a single pass, vertical, overhead or horizontal, without formwork, by hand, trowel or wet-spray.
- It is a repair mortar of the type covered by EN 1504-3 and meets the Class R4 thresholds, reaching approximately 70 MPa compressive strength at 28 days.
- No Australian Standard specifically governs proprietary concrete repair mortars.
- The published figures are typical Forspec R&D characteristic data.
- No accredited certificate is currently held; full classification testing to EN 1504-3 is available on request from Forspec.
Key applications
- Repair of damaged or spalled concrete on columns, beams, walls and soffits
- Patching and reinstatement around corroded reinforcement
- Bridge decks, tunnels, marine infrastructure and water-exposed structures
- Precast element defect repair and structural reinstatement
- Infrastructure exposed to impact, abrasion or environmental deterioration
Surface suitability
- Concrete (new concrete a minimum of 28 days old, all damaged, spalled and unsound material mechanically removed)
- Concrete (perimeter edges saw-cut square to a minimum depth of 5 mm, never feather-edged)
- Concrete (prepared to a sound, roughened CSP 4-6 profile free of laitance, dust, oil and contaminants)
- Concrete (saturated with clean water to a saturated surface dry condition, no standing water at placement)
- Exposed steel reinforcement (cleaned to bright metal, ISO 8501-1 Sa 2 and a half, and zinc-primed immediately)
Apply only between 5C and 35C ambient and substrate. Do not apply below 5C and falling, onto frozen substrates, or above 35C. Never exceed the mixing water dose of 3.6 L per 20kg bag, as overwatering reduces strength and delays setting. New concrete must be a minimum of 28 days old. Application thickness is 3-100mm per pass, with repairs deeper than 100mm built in successive layers. Do not apply to unstable or moving substrates, as reflective cracking will occur. Curing is mandatory: ACTFLEX CURESEAL or damp hessian and plastic sheeting for a minimum of 72 hours, and the surface must not be allowed to dry, or be exposed to rain, hose water or traffic, in the first 24 hours. Use ACTFLEX EP250 as the primer for immersed or wet-exposure conditions. Never re-temper or reuse stiffened mortar. The wet mix is alkaline, contains portland cement and may contain respirable crystalline silica: wear a P2 dust respirator, chemical-resistant gloves, eye protection and covering clothing, and read the SDS before use.
Shipping and returns
Technical documents
Why waterproofers use FORCRETE Panel Patch 20kg
Places 3mm to 100mm in a single pass, vertical, overhead and horizontal, without formwork
Shrinkage-compensated and polymer-modified, with bond to concrete above 2.0 MPa
How to apply FORCRETE Panel Patch 20kg
Step by step from the technical data sheet. Always read the full TDS before you start.
-
1
Mechanically remove all damaged, spalled and unsound concrete from the repair zone
-
2
Saw-cut perimeter edges to a minimum depth of 5 mm with square edges and do not feather-edge
-
3
Prepare the exposed substrate to a sound, roughened CSP 4-6 profile, free of laitance, dust, oil and contaminants
-
4
Clean exposed reinforcement to bright metal (ISO 8501-1 Sa 2 and a half) and prime it immediately
-
5
Apply a single-pack zinc-rich primer to the cleaned reinforcement only, keeping it off the surrounding concrete
-
6
Saturate the substrate with clean water and bring it to a saturated surface dry condition with no standing water
-
7
Prime all prepared concrete with ACTFLEX 300, or with ACTFLEX EP250 where the completed repair will be damp, porous or immersed
-
8
Measure exactly 3.6 L of clean potable water per 20kg bag into a clean vessel first
-
9
Add the powder gradually and continuously with the mixer running at slow speed, never in one dump
-
10
Mix 3 to 5 minutes at medium speed with a high-torque drill and spiral paddle at 400-600 RPM, pause 1 minute for air release, then re-mix 30 seconds
-
11
Place the mortar while the primer is still at the tack stage, working from the base of the repair upward
-
12
Press the mortar firmly into the substrate and fully around reinforcement bars to eliminate voids, then compact with trowel pressure or light tamping
-
13
Build repairs deeper than 100mm in successive layers, allowing each layer to stiffen and lightly scarifying it to key the next pass
-
14
Finish with a steel float for smooth surfaces or a sponge float for texture once the mortar begins to firm at initial set
-
15
Cure immediately after finishing with ACTFLEX CURESEAL or damp hessian and plastic sheeting, maintained for a minimum of 72 hours
-
16
Protect the repair from drying, rainfall, hose water and traffic for the first 24 hours
-
17
Allow a minimum of 7 days, with moisture verified, before overcoating with FORSPEC membranes and coatings
Specifications
Every figure from the technical data sheet, in one table.
Customer reviews
Common questions
-
What is FORCRETE Panel Patch used for?
FORCRETE Panel Patch (also known as FORCRETE 100) is a high-build, high-strength repair mortar for structural patching - vertical, horizontal, and overhead concrete repairs. Bonds to concrete and reinforcing steel.
-
What strength does it reach?
FORCRETE Panel Patch achieves 70 MPa compressive strength at 28 days - one of the highest-strength repair mortars in the Forspec range. Bond strength to concrete exceeds 2 MPa - typically exceeds parent concrete strength.
-
Thickness range?
Horizontal applications: 10-180mm in a single layer. Vertical and overhead: 5-100mm. Initial set in 1.5 hours, final set in 2.5 hours. Mix 20kg powder with 3.6L water.
-
What about reinforcing steel?
Fibre-reinforced and polymer-modified. Resists chloride ingress and carbonation - so it actively helps protect embedded rebar in coastal and aggressive environments. Use BR10 ZP zinc-rich primer on exposed rebar.
-
Yield from a 20kg bag?
20kg powder plus 3.6L water yields approximately 11.1-11.5L of mixed mortar. Density 2.1 g/cm³. The high strength and dense matrix make it suitable for marine and infrastructure repair.
Ready to order?
Dispatched same or next business day from Roselands NSW. Questions? Call the team on (02) 8021 3517.