Bed the tape into a wet base coat of the specified FORSPEC membrane with a steel trowel or spatula, then apply a second coat over the entire tape length to fully encapsulate itConfirm substrates are clean, dry, structurally sound and free of laitance, dust, oil, grease, paint, sealers, curing compounds and all other bond-inhibiting contaminants
Mechanically prepare dense, burnished or coated surfaces by grinding or light abrasion to expose sound substrate, then vacuum the area thoroughly
Make concrete surfaces smooth and free of surface ridges, sharp projections, fins and voids
Ensure junction zones are smooth and continuous for a minimum of 200 mm in every direction from the corner, including the wall upturn
Cut out and reinstate any weak, hollow or drummy render or screed; renders and screeds must be fully cured, crack-free and solidly bonded
Reinstate defects, voids and blowholes with FORBUILD 100 or FORCRETE 100, finished flush and cured
Remove all loose fasteners, screws, nails and debris from wall and floor sheet surfaces
Confirm any required primer has been applied and is fully dry
Pre-fill cracks and static joints wider than 3 mm with ACTFLEX 75FC or ACTFLEX MS PRO and allow to cure
Apply a generous, continuous base coat of the specified FORSPEC membrane at the junction, wide enough to receive the full tape width plus margin on both sides
While the membrane is still wet, centre the tape over the junction so the elastomeric centre spans the joint and the mesh wings lie flat on both planes
Press the tape into the wet membrane with a steel trowel or spatula, working from the centre outwards to expel air, wrinkles and dry zones
Overlap tape ends by a minimum of 50 mm, fully embedded in membrane at the lap
Cut internal corners at 45 degrees and lap or mitre neatly, keeping the centre of the tape continuous and uninterrupted around the corner
Pre-form or cut external corners to the corner shape with continuous overlap, fully saturated on both planes
Allow the base coat to partially set, then apply the second coat of membrane over the entire tape length, fully embedding and encapsulating the tape
Inspect the installed detail for hollow zones, wrinkles, dry mesh or felt, and lifted edges; cut out and re-detail any defective length before continuing
Flood test after full cure of the membrane system, then tile or cover